project status complete

 

 

Project Overview

We have delivered a project to alleviate internal and external sewer flooding in and around David Dale Avenue in Stewarton, East Ayrshire.

The capacity of the local sewer network has been increased to make it less prone to overflowing.

At a Glance

  • £2.2million investment
  • Work carried out in two phases
  • Delivered by George Leslie

David Dale Avenue Stewarton Flood Alleviation

Increased Capacity

Most of the work was  carried out in the grounds of Lainshaw Primary School where larger sewer pipes were laid

What We Are Doing

Work on the first phase began in July 2022 and was completed a year later. Designed to alleviate the majority of internal and external flooding, a new upgraded sewer was installed along David Dale Avenue and through an area of mature woodland.

Phase two has seen an upgraded sewer pipe installed in the grounds of Lainshaw Primary School.

We used directional drilling along with the traditional open cut method to minimise disruption to the local community. It involved sinking two small shafts into the ground in the playground area.

David Dale Avenue Stewarton Flood Alleviation

Larger sewer pipes have been installed

David Dale Avenue Stewarton Flood Alleviation

Work was carried out in two phases

Why We Are Doing It

Properties along David Dale Avenue in Stewarton had been prone to internal and external sewer flooding during periods of heavy rain. There has also been a significant increase in the local population and new properties being built.

David Dale Avenue

The capacity of the local sewer network has been increased

David Dale Avenue

Work on the second phase began in July 2025

Update February 2026

We have now completed the second and final phase of the upgrade to the local network and are currently demobilising from site.

Nearly 150 metres of new 1800mm pipe has been installed at depths of up to 8.5 metres from Morton Road, under Lainshaw Primary School’s playing field to just south of the A735.

Specialist landscaping contractors will be on site over the coming months – weather permitting – to install turf and we will be erecting a new fence and carrying out some planting at the school.

We are extremely grateful to everyone for their patience, cooperation and understanding.

David Dale Avenue Stewarton